Village of Three Oaks

Water System Improvements Project

1

1

Project Introduction

This project involves the replacement of water mains throughout the Village of Three Oaks, Michigan.  In addition to the replacement of water main, improvements to the control system, wells, and repainting of the water tower will all be completed.

Current Contractor Schedule

Date Location
4/11/11-8/15/11 Streets north of US-12
7/15/11-9/30/11 South Elm Street
9/15/11-10/31/11 West Maple Street
9/19/11-11/15/11

Streets south of US-12

Contract A – Water Main and Appurtenances

The Contractor will be working on the following roads between April 11, 2011, and November 15, 2011:

Beech St. Buckeye St. Cedar St Cherry St. Chestnut St.
Chicago St. Featherbone St. Hickory St.   Linden St. Locust St.
Magnolia St. Maple St. Michigan St. North Elm St. Oak St.
Orange St. Paw Paw St. Pine St. Poplar St. Sherwood St.
South Elm St.   Walnut St.      

Contract B – Production Well work on the well buildings will take place between April 4, 2011, and July 13, 2011.

Contract C – Tower Repaintingis scheduled to begin August 15, 2011.

Contact Information

On Site Representative
Bill Pagel
Cell Phone: (269) 605-9681

Project Manager for Water System
Dan Yerks, P.E.
Office Phone: (269) 927-0100